Tritorc Logo

Hot Tapping Operation Completed in 3 Days for ONGC at NQP Offshore Platform

Updated on: June 4, 2025
Category: ,
Tritorc Team holding the tocken after sucessful hot tapping operation

As part of the Pipeline Replacement Project, ONGC and its EPC contractor undertook a critical offshore infrastructure upgrade at the NQP Platform. A major requirement was to perform a Hot Tapping operation on a live 16-inch pipeline to introduce a new 12-inch branch connection.

Given the complexity and high-risk nature of the task, TRITORC was selected as the specialized engineering partner for executing the operation without interrupting ongoing hydrocarbon flow.

Hot Tapping Challenge in an Offshore Environment

Offshore Hot Tapping presents multiple operational challenges. The confined working area on the platform, dynamic marine environment, and continuous pipeline pressure required a solution that ensured precision, safety, and minimal disruption.

The target pipeline was a 16” line operating at a pressure of 7.5 to 9 bar, made of ASTM A106 Gr. B material, requiring exacting weld procedures and equipment configuration. Moreover, safety compliance, detailed documentation, and third-party inspections by both the EPC contractor and ONGC were non-negotiable parts of the workflow.

Custom-Engineered Solution

TRITORC’s team, led by Project Manager Sarfaraz Nawaz Taj, Operations Coordinator Imran Ansari, and Design Engineer Rohit Harpude, devised a comprehensive execution strategy. The team selected a 16” x 12” weld-on branch fitting fabricated to ASME B31.3 standards and supported it with a custom saddle clamp to prevent stress during cutting and tapping.

The hot tapping machine, a 16” full-bore hydraulic system, was configured to execute the operation while maintaining structural integrity and ensuring accurate coupon retrieval.

Setting up fittings for installing the hot tap machine
Operator performing long seam welding
Operator performing long seam welding
Hot Tapping machine installation done with valve.
Hot Tapping machine installation done with valve.

Every component used was pre-tested, including the branch tee and the split flange setup. A custom-designed guide support system was installed to ensure alignment under offshore conditions. Multiple approval cycles from L&T and ONGC ensured that all safety, material, and weld parameters were meticulously reviewed and cleared before execution.

Execution and Operations

The operation began with the welding of the branch tee onto the live 16” line, followed by hydrotesting and NDT (Non-Destructive Testing) of the weld joint. Once integrity was confirmed, TRITORC mounted the hot tapping equipment and initiated the tapping process. The hydraulic power pack and cutting system operated smoothly, maintaining consistent feed and torque.

The coupon was successfully cut and retrieved, ensuring that no debris entered the pipeline. The tapping process was completed well within the stipulated time, despite challenging offshore conditions. Throughout the operation, the TRITORC team followed a strict Job Safety Analysis (JSA), with offshore HSE representatives from both the client and end user monitoring and approving each step.

Successful Completion and Impact

The Hot Tapping operation was completed without any shutdown, downtime, or safety incident. ONGC’s hydrocarbon supply remained uninterrupted throughout, showcasing TRITORC’s ability to execute high-risk interventions safely and efficiently. The operation not only met all technical specifications but also earned commendations from both L&T and ONGC for its smooth execution and attention to detail.

The collaboration between TRITORC’s technical and field teams played a key role in the successful completion. Rohit Harpude ensured that all engineering calculations and equipment specs were aligned with offshore requirements. Imran Ansari coordinated operations and logistics with precision, while Sarfaraz Nawaz Taj led the execution with clarity and strong site leadership.

Hot Tapping ONGC

Conclusion

TRITORC’s successful execution of the Hot Tapping operation at the NQP Platform reinforces its position as a leader in live-line and specialized offshore services. The company’s engineered approach, strict safety practices, and experienced team enabled a flawless operation under demanding offshore conditions.

As India continues to invest in critical oil and gas infrastructure, TRITORC remains a reliable partner for complex field interventions that demand expertise, safety, and speed.

Whether for emergency tie-ins, system modifications, or pressure containment work, the company’s track record in delivering high-integrity solutions in active systems reflects a deep-rooted commitment to operational excellence, asset protection, and project timelines.

Related Blogs
  • Tritorc Leak Testing

    Nitrogen-Helium Leak Testing – SARB Accelerated Growth Project, UAE

    Challenge As part of ADNOC’s SARB Accelerated Growth Project, early tie-in of production wells at AlQatia (SARB North Artificial Island) demanded a highly precise and reliable leak detectionmethod for critical process piping. The scope involved testing 1” to 6” piping for SLOT-58 andSLOT-35 under high pressures (up to 276 Barg), where even micro-leaks could pose […]
    June 4, 2025
    Puneet Avatar
  • Pamban Bridge

    TRITORC tools Empowering Construction of The New Pamban Bridge

    The inauguration of the New Pamban Bridge marks a significant milestone in India’s infrastructural advancements. “The blend of historical reverence with modern engineering.” TRITORC is honored to have contributed to this landmark project by supplying specialized bolting tools required for its construction. Pamban Bridge: A Legacy Rebuilt The Pamban Bridge, inaugurated in 1914, being India’s […]
    June 2, 2025
    Puneet Avatar
  • Wind TurbineSite

    Tritorc Powering Greener Future by Bolting Wind Turbines – Case Study

    A major wind energy project has begun: one that will play a key role in India’s vision toward sustainable power. The goal?  The goal is to produce 30 GW of wind energy per hour by installing numerous wind turbines in a span of five years. It is a big mission, and Tritorc is all set […]
    June 2, 2025
    Puneet Avatar
  • Tritorc in Uzbekistan

    Tritorc’s Retubing Maintenance Project in Uzbekistan: A Comprehensive Case Study

    In a landmark project showcasing technical prowess and industry-leading capabilities, Tritorc has successfully completed a crucial heat exchanger retubing and maintenance operation in Uzbekistan’s oil and gas sector. This project, focusing on oxygen preheaters, highlights Tritorc’s position as a complete solution provider for heat transfer equipment maintenance in challenging environments.  Tritorc’s engineers demonstrated their versatility […]
    May 30, 2025
    Simran Avatar
  • NCOC Karabatan Tritorc

    Engineering Excellence in High-Pressure Onshore Operations: The Karabatan NCOC Project

    Kazakhstan’s Karabatan Onshore Processing Facility, part of the North Caspian Project, exemplifies cutting-edge engineering in one of the world’s most challenging onshore environments.  Developed under the North Caspian Production Sharing Agreement (NCPSA), this facility processes hydrocarbons from the Kashagan field, one of the largest oil discoveries in recent decades. The project holds an estimated 9–13 […]
    March 18, 2025
    Puneet Avatar
  • Hot tapping solution

    Overcoming Pipeline Challenges: TRITORC’s Hot Tapping Solution as a Game Changer

    In today’s busy and continuous running world, industries like oil & gas, petrochemicals, and energy depend and opt for continuous work operations. However, maintaining the desired level of efficiency in a constant working industry is not an  easy task. Pipelines form the lifelines of these industries, which constantly face challenges that can affect critical processes, […]
    May 29, 2025
    Puneet Avatar
  • oil-gas-industry

    The Future of Oil and Gas Maintenance—How Tritorc is helping solve Critical Challenges

    Oil and gas is at a crossroad right now because of the growing demand, new technology, and the environmental pressures that will eventually change the face of operations. One of the biggest issues is still that of effective maintenance, specifically the avoidance of forced outages, the extension of asset life, and the upholding of high […]
    March 28, 2025
    Puneet Avatar
  • Retubing-application

    Retubing Project at Samsung Abu Dhabi Oil and Gas Plant

    Project Overview In February 2024, ADNOC approved a critical retubing project at the Samsung Abu Dhabi Oil and Gas Refinery Plant. The primary objective was to address significant operational issues, including pressure drops and leaks in the heat exchangers, which compromised the plant’s efficiency and safety. The project commenced on February 26, 2024, with an […]
    March 24, 2025
    Omkar Avatar
  • Offshore

    Hot Tapping Operation at B193, 28 Hours from shore

    Tritorc secured a challenging offshore hot tapping project from one of the largest MNCs in the world through a strategic and collaborative approach. Leveraging strong industry reputation and expertise in hot tapping solutions, Tritorc engaged proactively with the client’s procurement and engineering team. Introduction: The hot tapping project at an offshore process platform aimed to […]
    April 4, 2025
    Omkar Avatar
  • Hot-Tapping

    How to Prepare a Pipe for Hot Tapping

    Hot Tapping or pressure tapping, is a method for connecting a branch to a “hot” or operational line. By drilling or cutting, the hot tapping procedure enables a connection into a pressurized in-service operating system. In the hot tap procedure, a branch connection and valve are attached to the exterior of an operational pipeline. The […]
    April 4, 2025
    Omkar Avatar
  • Hot-Tapping-and-line-stopping

    Difference between Hot Tapping and Line Stopping

    When a certain section of pipe is damaged or rusted or requires modifications such as addition or removal of a valve, and the output of the particular pipeline or plant cannot be halted, then the particular pipeline must have a conduit attached to it for temporary or permanent purposes. This process shall go one step […]
    April 7, 2025
    Omkar Avatar
  • Hot Tapping and Line Stopping

    A Brief Introduction to Hot Tapping & Line Stopping

    Pipelines are a conveyance medium for various fluids that are necessary to keep civilization functional. To keep these critical pieces of infrastructure functional, several tools, accessories, and machinery are needed to keep up with the requirements of their maintenance, repair, and overhaul cycles.  Productivity is critical for maintaining profitability for the large economies of scale […]
    April 7, 2025
    Omkar Avatar

Leave a Reply

Your email address will not be published. Required fields are marked *